UPRERAPRJ10510

Antriksh Golf Link Phase 2

Antriksh Golf Link Phase 2 is on the UP RERA register as UPRERAPRJ10510. Promoter on the list: M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH. District: Gautam Buddha Nagar. List project type: Residential. List end date: 24-11-2021. Verify on up-rera.in.

Project name
Antriksh Golf Link Phase 2
Promoter
M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH
UP RERA registration number
UPRERAPRJ10510
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
Ongoing
Start date on the registered-projects list
01-03-2015
End date on the registered-projects list
24-11-2021
Registration date
14-08-2017
Original start date on the summary
19-02-2013
Modified start date on the summary
01-03-2015
Declared date of completion on the summary
25-05-2021

Extension rows

Extension fromExtension upto
25-05-202124-11-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)

Calculated from those dates

Registration to list end date

51 whole months from the registration date 14-08-2017 to the end date on the registered-projects list 24-11-2021.

Original start to declared completion

99 whole months from the original start date 19-02-2013 to the declared completion date 25-05-2021.

Extension rows

The project summary lists 1 extension row. The last “Extension Upto” text is 24-11-2021 (Six months extension in view of force majeure caused by covid-19 pandemic).

List end date against declared completion

5 whole months from the declared completion date 25-05-2021 to the list end date 24-11-2021.

List end date against the fetch date

58 whole months from the list end date 24-11-2021 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this Antriksh Golf Link Phase 2 record

Antriksh Golf Link Phase 2 is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ10510. The promoter text is M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH. The project address cell is blank on this row.

The list project type is Residential. The summary project type is Ongoing. Registration date: 14-08-2017. Start date on the list: 01-03-2015. End date on the list: 24-11-2021. Declared completion on the summary: 25-05-2021.

A Antriksh Golf Link Phase 2 price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about Antriksh Golf Link Phase 2

What is the UP RERA registration for Antriksh Golf Link Phase 2?

The 2026-10-14 Gautam Buddha Nagar extract lists Antriksh Golf Link Phase 2 as UPRERAPRJ10510. Promoter on that row: M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a Antriksh Golf Link Phase 2 price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean Antriksh Golf Link Phase 2 is ready to move?

No. The list end date is 24-11-2021. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish Antriksh Golf Link Phase 2 reviews?

No. This page does not publish star ratings or copied portal reviews.

When was Antriksh Golf Link Phase 2 registered?

Registration date on the extract: 14-08-2017. Start date on the registered-projects list: 01-03-2015. Declared completion on the summary: 25-05-2021.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.