Registration to list end date
72 whole months from the registration date 05-02-2019 to the end date on the registered-projects list 25-02-2025.
UPRERAPRJ236478
CYBERTHUM PHASE A is on the UP RERA register as UPRERAPRJ236478. Promoter on the list: MAX-DIGI INFOTECH PRIVATE LIMITED. District: Gautam Buddha Nagar. List project type: Commercial. List end date: 25-02-2025. Verify on up-rera.in.
| Extension from | Extension upto |
|---|---|
| 01-12-2022 | 30-05-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30-05-2023 | 25-12-2023 |
| 25-12-2023 | 25-02-2025 |
72 whole months from the registration date 05-02-2019 to the end date on the registered-projects list 25-02-2025.
47 whole months from the original start date 01-01-2019 to the declared completion date 01-12-2022.
The project summary lists 3 extension rows. The last “Extension Upto” text is 25-02-2025.
26 whole months from the declared completion date 01-12-2022 to the list end date 25-02-2025.
19 whole months from the list end date 25-02-2025 to the fetch date 2026-10-14.
Official UP RERA project summary
List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.
CYBERTHUM PHASE A is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ236478. The promoter text is MAX-DIGI INFOTECH PRIVATE LIMITED. The project address cell is blank on this row.
The list project type is Commercial. The summary project type is New. Registration date: 05-02-2019. Start date on the list: 01-01-2019. End date on the list: 25-02-2025. Declared completion on the summary: 01-12-2022.
A CYBERTHUM PHASE A price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.
Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.
The 2026-10-14 Gautam Buddha Nagar extract lists CYBERTHUM PHASE A as UPRERAPRJ236478. Promoter on that row: MAX-DIGI INFOTECH PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.
No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.
No. The list end date is 25-02-2025. The project type on the extract is New. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.
No. This page does not publish star ratings or copied portal reviews.
Registration date on the extract: 05-02-2019. Start date on the registered-projects list: 01-01-2019. Declared completion on the summary: 01-12-2022.
Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.
Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.