UPRERAPRJ7115

F PREMIERE (PHASE 1)

F PREMIERE (PHASE 1) is on the UP RERA register as UPRERAPRJ7115. Promoter on the list: HOME AND SOUL INFRATECH PRIVATE LIMITED. District: Gautam Buddha Nagar. List project type: Residential. List end date: 31-12-2025. Verify on up-rera.in.

Project name
F PREMIERE (PHASE 1)
Promoter
HOME AND SOUL INFRATECH PRIVATE LIMITED
UP RERA registration number
UPRERAPRJ7115
District
Gautam Buddha Nagar
Tehsil
Dadri
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
Ongoing
Start date on the registered-projects list
10-10-2014
End date on the registered-projects list
31-12-2025
Registration date
01-08-2017
Original start date on the summary
10-10-2014
Modified start date on the summary
10-10-2014
Declared date of completion on the summary
30-06-2021

Extension rows

Extension fromExtension upto
30-06-202129-12-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
29-12-202128-09-2023
28-09-202330-09-2024
30-09-202431-03-2025
31-03-202531-12-2025

Calculated from those dates

Registration to list end date

100 whole months from the registration date 01-08-2017 to the end date on the registered-projects list 31-12-2025.

Original start to declared completion

80 whole months from the original start date 10-10-2014 to the declared completion date 30-06-2021.

Extension rows

The project summary lists 5 extension rows. The last “Extension Upto” text is 31-12-2025.

List end date against declared completion

54 whole months from the declared completion date 30-06-2021 to the list end date 31-12-2025.

List end date against the fetch date

9 whole months from the list end date 31-12-2025 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this F PREMIERE (PHASE 1) record

F PREMIERE (PHASE 1) is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ7115. The promoter text is HOME AND SOUL INFRATECH PRIVATE LIMITED. The project address cell is blank on this row.

The list project type is Residential. The summary project type is Ongoing. Registration date: 01-08-2017. Start date on the list: 10-10-2014. End date on the list: 31-12-2025. Declared completion on the summary: 30-06-2021.

A F PREMIERE (PHASE 1) price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about F PREMIERE (PHASE 1)

What is the UP RERA registration for F PREMIERE (PHASE 1)?

The 2026-10-14 Gautam Buddha Nagar extract lists F PREMIERE (PHASE 1) as UPRERAPRJ7115. Promoter on that row: HOME AND SOUL INFRATECH PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a F PREMIERE (PHASE 1) price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean F PREMIERE (PHASE 1) is ready to move?

No. The list end date is 31-12-2025. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish F PREMIERE (PHASE 1) reviews?

No. This page does not publish star ratings or copied portal reviews.

When was F PREMIERE (PHASE 1) registered?

Registration date on the extract: 01-08-2017. Start date on the registered-projects list: 10-10-2014. Declared completion on the summary: 30-06-2021.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.

Other records

Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.

WhatsApp