Registration to list end date
40 whole months from the registration date 10-08-2017 to the end date on the registered-projects list 07-01-2021.
UPRERAPRJ8813
Footprints for Commercial Use, Sec-22A is on the UP RERA register as UPRERAPRJ8813. Promoter on the list: YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY. District: Gautam Buddha Nagar. List project type: Commercial. List end date: 07-01-2021. Verify on up-rera.in.
| Extension from | Extension upto |
|---|---|
| 09-07-2019 | 08-07-2020 |
| 08-07-2020 | 07-01-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
40 whole months from the registration date 10-08-2017 to the end date on the registered-projects list 07-01-2021.
17 whole months from the original start date 10-01-2018 to the declared completion date 09-07-2019.
The project summary lists 2 extension rows. The last “Extension Upto” text is 07-01-2021 (Six months extension in view of force majeure caused by covid-19 pandemic).
17 whole months from the declared completion date 09-07-2019 to the list end date 07-01-2021.
69 whole months from the list end date 07-01-2021 to the fetch date 2026-10-14.
Official UP RERA project summary
List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.
Footprints for Commercial Use, Sec-22A is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ8813. The promoter text is YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY. The project address cell is blank on this row.
The list project type is Commercial. The summary project type is Ongoing. Registration date: 10-08-2017. Start date on the list: 10-01-2018. End date on the list: 07-01-2021. Declared completion on the summary: 09-07-2019.
A Footprints for Commercial Use, Sec-22A price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.
Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.
The 2026-10-14 Gautam Buddha Nagar extract lists Footprints for Commercial Use, Sec-22A as UPRERAPRJ8813. Promoter on that row: YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY. Confirm the same number on up-rera.in. This page does not invent a second number.
No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.
No. The list end date is 07-01-2021. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.
No. This page does not publish star ratings or copied portal reviews.
Registration date on the extract: 10-08-2017. Start date on the registered-projects list: 10-01-2018. Declared completion on the summary: 09-07-2019.
Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.
Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.