UPRERAPRJ6819

Hillston By URBTech- Phase 1-Tower E&F

Hillston By URBTech- Phase 1-Tower E&F is on the UP RERA register as UPRERAPRJ6819. Promoter on the list: GOLFGREEN BUILDCON PRIVATE LIMITED. District: Gautam Buddha Nagar. List project type: Residential. List end date: 30-01-2024. Verify on up-rera.in.

Project name
Hillston By URBTech- Phase 1-Tower E&F
Promoter
GOLFGREEN BUILDCON PRIVATE LIMITED
UP RERA registration number
UPRERAPRJ6819
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
Ongoing
Start date on the registered-projects list
01-08-2017
End date on the registered-projects list
30-01-2024
Registration date
09-08-2017
Original start date on the summary
04-09-2013
Modified start date on the summary
01-08-2017
Declared date of completion on the summary
31-07-2023

Extension rows

Extension fromExtension upto
31-07-202330-01-2024 (Six months extension in view of force majeure caused by covid-19 pandemic)

Calculated from those dates

Registration to list end date

77 whole months from the registration date 09-08-2017 to the end date on the registered-projects list 30-01-2024.

Original start to declared completion

118 whole months from the original start date 04-09-2013 to the declared completion date 31-07-2023.

Extension rows

The project summary lists 1 extension row. The last “Extension Upto” text is 30-01-2024 (Six months extension in view of force majeure caused by covid-19 pandemic).

List end date against declared completion

5 whole months from the declared completion date 31-07-2023 to the list end date 30-01-2024.

List end date against the fetch date

32 whole months from the list end date 30-01-2024 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this Hillston By URBTech- Phase 1-Tower E&F record

Hillston By URBTech- Phase 1-Tower E&F is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ6819. The promoter text is GOLFGREEN BUILDCON PRIVATE LIMITED. The project address cell is blank on this row.

The list project type is Residential. The summary project type is Ongoing. Registration date: 09-08-2017. Start date on the list: 01-08-2017. End date on the list: 30-01-2024. Declared completion on the summary: 31-07-2023.

A Hillston By URBTech- Phase 1-Tower E&F price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about Hillston By URBTech- Phase 1-Tower E&F

What is the UP RERA registration for Hillston By URBTech- Phase 1-Tower E&F?

The 2026-10-14 Gautam Buddha Nagar extract lists Hillston By URBTech- Phase 1-Tower E&F as UPRERAPRJ6819. Promoter on that row: GOLFGREEN BUILDCON PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a Hillston By URBTech- Phase 1-Tower E&F price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean Hillston By URBTech- Phase 1-Tower E&F is ready to move?

No. The list end date is 30-01-2024. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish Hillston By URBTech- Phase 1-Tower E&F reviews?

No. This page does not publish star ratings or copied portal reviews.

When was Hillston By URBTech- Phase 1-Tower E&F registered?

Registration date on the extract: 09-08-2017. Start date on the registered-projects list: 01-08-2017. Declared completion on the summary: 31-07-2023.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.