UPRERAPRJ783018

NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14)

NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is on the UP RERA register as UPRERAPRJ783018. Promoter on the list: G3 ASPIRE NIRALA GOLD LLP NIRALA HOUSING PRIVATE LIMITED. District: Gautam Buddha Nagar. List project type: Residential. List end date: 20-02-2025. Verify on up-rera.in.

Project name
NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14)
Promoter
G3 ASPIRE NIRALA GOLD LLP NIRALA HOUSING PRIVATE LIMITED
UP RERA registration number
UPRERAPRJ783018
District
Gautam Buddha Nagar
Tehsil
311
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
New
Start date on the registered-projects list
01-07-2022
End date on the registered-projects list
20-02-2025
Registration date
09-08-2022
Original start date on the summary
01-07-2022
Modified start date on the summary
Not listed on UP RERA
Declared date of completion on the summary
20-02-2025

Extension rows

The project summary does not list an extension row.

Calculated from those dates

Registration to list end date

30 whole months from the registration date 09-08-2022 to the end date on the registered-projects list 20-02-2025.

Original start to declared completion

31 whole months from the original start date 01-07-2022 to the declared completion date 20-02-2025.

Extension rows

The project summary does not list an extension row.

List end date against the fetch date

19 whole months from the list end date 20-02-2025 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) record

NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ783018. The promoter text is G3 ASPIRE NIRALA GOLD LLP NIRALA HOUSING PRIVATE LIMITED. The project address cell is blank on this row.

The list project type is Residential. The summary project type is New. Registration date: 09-08-2022. Start date on the list: 01-07-2022. End date on the list: 20-02-2025. Declared completion on the summary: 20-02-2025.

A NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14)

What is the UP RERA registration for NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14)?

The 2026-10-14 Gautam Buddha Nagar extract lists NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) as UPRERAPRJ783018. Promoter on that row: G3 ASPIRE NIRALA GOLD LLP NIRALA HOUSING PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is ready to move?

No. The list end date is 20-02-2025. The project type on the extract is New. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) reviews?

No. This page does not publish star ratings or copied portal reviews.

When was NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) registered?

Registration date on the extract: 09-08-2022. Start date on the registered-projects list: 01-07-2022. Declared completion on the summary: 20-02-2025.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.

Other records

Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.

WhatsApp