Registration to list end date
12 whole months from the registration date 28-01-2026 to the end date on the registered-projects list 27-02-2027.
UPRERAPRJ819615/01/2026
Page 3 Noida is on the UP RERA register as UPRERAPRJ819615/01/2026. Promoter on the list: PAGE3 BUILDTECH PRIVATE LIMITED. Project address: B-56. List project type: Residential. List end date: 27-02-2027. Verify on up-rera.in.
| Extension from | Extension upto |
|---|---|
| 31-10-2026 | 27-02-2027 (Extension of validity on account of Force Majeure as per MoHUA advisory dated 31-07-2026) |
12 whole months from the registration date 28-01-2026 to the end date on the registered-projects list 27-02-2027.
57 whole months from the original start date 01-01-2022 to the declared completion date 31-10-2026.
The project summary lists 1 extension row. The last “Extension Upto” text is 27-02-2027 (Extension of validity on account of Force Majeure as per MoHUA advisory dated 31-07-2026).
3 whole months from the declared completion date 31-10-2026 to the list end date 27-02-2027.
4 whole months from the fetch date 2026-10-14 to the list end date 27-02-2027.
Official UP RERA project summary
List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.
Page 3 Noida is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ819615/01/2026. The promoter text is PAGE3 BUILDTECH PRIVATE LIMITED. The project address is B-56.
The list project type is Residential. The summary project type is New. Registration date: 28-01-2026. Start date on the list: 01-01-2022. End date on the list: 27-02-2027. Declared completion on the summary: 31-10-2026.
A Page 3 Noida price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.
Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.
The 2026-10-14 Gautam Buddha Nagar extract lists Page 3 Noida as UPRERAPRJ819615/01/2026. Promoter on that row: PAGE3 BUILDTECH PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.
No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.
No. The list end date is 27-02-2027. The project type on the extract is New. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.
No. This page does not publish star ratings or copied portal reviews.
Registration date on the extract: 28-01-2026. Start date on the registered-projects list: 01-01-2022. Declared completion on the summary: 31-10-2026.
Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.