UPRERAPRJ15192

RATAN PEARLS (PHASE-II)

RATAN PEARLS (PHASE-II) is on the UP RERA register as UPRERAPRJ15192. Promoter on the list: RATAN BUILDTECH PRIVATE LIMITED. District: Gautam Buddha Nagar. List project type: Residential. List end date: 28-12-2023. Verify on up-rera.in.

Project name
RATAN PEARLS (PHASE-II)
Promoter
RATAN BUILDTECH PRIVATE LIMITED
UP RERA registration number
UPRERAPRJ15192
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
New
Start date on the registered-projects list
01-04-2018
End date on the registered-projects list
28-12-2023
Registration date
15-02-2018
Original start date on the summary
01-04-2018
Modified start date on the summary
Not listed on UP RERA
Declared date of completion on the summary
30-09-2021

Extension rows

Extension fromExtension upto
30-09-202129-03-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)
29-03-202228-12-2023

Calculated from those dates

Registration to list end date

70 whole months from the registration date 15-02-2018 to the end date on the registered-projects list 28-12-2023.

Original start to declared completion

41 whole months from the original start date 01-04-2018 to the declared completion date 30-09-2021.

Extension rows

The project summary lists 2 extension rows. The last “Extension Upto” text is 28-12-2023.

List end date against declared completion

26 whole months from the declared completion date 30-09-2021 to the list end date 28-12-2023.

List end date against the fetch date

33 whole months from the list end date 28-12-2023 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this RATAN PEARLS (PHASE-II) record

RATAN PEARLS (PHASE-II) is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ15192. The promoter text is RATAN BUILDTECH PRIVATE LIMITED. The project address cell is blank on this row.

The list project type is Residential. The summary project type is New. Registration date: 15-02-2018. Start date on the list: 01-04-2018. End date on the list: 28-12-2023. Declared completion on the summary: 30-09-2021.

A RATAN PEARLS (PHASE-II) price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about RATAN PEARLS (PHASE-II)

What is the UP RERA registration for RATAN PEARLS (PHASE-II)?

The 2026-10-14 Gautam Buddha Nagar extract lists RATAN PEARLS (PHASE-II) as UPRERAPRJ15192. Promoter on that row: RATAN BUILDTECH PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a RATAN PEARLS (PHASE-II) price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean RATAN PEARLS (PHASE-II) is ready to move?

No. The list end date is 28-12-2023. The project type on the extract is New. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish RATAN PEARLS (PHASE-II) reviews?

No. This page does not publish star ratings or copied portal reviews.

When was RATAN PEARLS (PHASE-II) registered?

Registration date on the extract: 15-02-2018. Start date on the registered-projects list: 01-04-2018. Declared completion on the summary: 30-09-2021.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.

Other records

Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.

WhatsApp