Registration to list end date
62 whole months from the registration date 09-08-2017 to the end date on the registered-projects list 09-10-2022.
UPRERAPRJ7228
RYNE is on the UP RERA register as UPRERAPRJ7228. Promoter on the list: PRIMROSE INFRATECH P LTD. District: Gautam Buddha Nagar. List project type: Residential. List end date: 09-10-2022. Verify on up-rera.in.
| Extension from | Extension upto |
|---|---|
| 10-04-2022 | 09-10-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
62 whole months from the registration date 09-08-2017 to the end date on the registered-projects list 09-10-2022.
107 whole months from the original start date 11-04-2013 to the declared completion date 10-04-2022.
The project summary lists 1 extension row. The last “Extension Upto” text is 09-10-2022 (Six months extension in view of force majeure caused by covid-19 pandemic).
5 whole months from the declared completion date 10-04-2022 to the list end date 09-10-2022.
48 whole months from the list end date 09-10-2022 to the fetch date 2026-10-14.
Official UP RERA project summary
List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.
RYNE is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ7228. The promoter text is PRIMROSE INFRATECH P LTD. The project address cell is blank on this row.
The list project type is Residential. The summary project type is Ongoing. Registration date: 09-08-2017. Start date on the list: 11-04-2013. End date on the list: 09-10-2022. Declared completion on the summary: 10-04-2022.
A RYNE price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.
Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.
The 2026-10-14 Gautam Buddha Nagar extract lists RYNE as UPRERAPRJ7228. Promoter on that row: PRIMROSE INFRATECH P LTD. Confirm the same number on up-rera.in. This page does not invent a second number.
No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.
No. The list end date is 09-10-2022. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.
No. This page does not publish star ratings or copied portal reviews.
Registration date on the extract: 09-08-2017. Start date on the registered-projects list: 11-04-2013. Declared completion on the summary: 10-04-2022.
Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.
Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.