UPRERAPRJ1746

SAMRIDHI LUXURIYA AVENUE

SAMRIDHI LUXURIYA AVENUE is on the UP RERA register as UPRERAPRJ1746. Promoter on the list: SAMRIDHI INFRA SQUARE PRIVATE LIMITED. Project address: Gautam budh nagar. List project type: Residential. List end date: 29-03-2025. Verify on up-rera.in.

Project name
SAMRIDHI LUXURIYA AVENUE
Promoter
SAMRIDHI INFRA SQUARE PRIVATE LIMITED
UP RERA registration number
UPRERAPRJ1746
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Project address
Gautam budh nagar
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
Ongoing
Start date on the registered-projects list
25-02-2017
End date on the registered-projects list
29-03-2025
Registration date
27-07-2017
Original start date on the summary
25-02-2017
Modified start date on the summary
25-02-2017
Declared date of completion on the summary
31-12-2022

Extension rows

Extension fromExtension upto
31-12-202230-06-2023 (Six months extension in view of force majeure caused by covid-19 pandemic)
30-06-202329-03-2025

Calculated from those dates

Registration to list end date

92 whole months from the registration date 27-07-2017 to the end date on the registered-projects list 29-03-2025.

Original start to declared completion

70 whole months from the original start date 25-02-2017 to the declared completion date 31-12-2022.

Extension rows

The project summary lists 2 extension rows. The last “Extension Upto” text is 29-03-2025.

List end date against declared completion

26 whole months from the declared completion date 31-12-2022 to the list end date 29-03-2025.

List end date against the fetch date

18 whole months from the list end date 29-03-2025 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this SAMRIDHI LUXURIYA AVENUE record

SAMRIDHI LUXURIYA AVENUE is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ1746. The promoter text is SAMRIDHI INFRA SQUARE PRIVATE LIMITED. The project address is Gautam budh nagar.

The list project type is Residential. The summary project type is Ongoing. Registration date: 27-07-2017. Start date on the list: 25-02-2017. End date on the list: 29-03-2025. Declared completion on the summary: 31-12-2022.

A SAMRIDHI LUXURIYA AVENUE price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about SAMRIDHI LUXURIYA AVENUE

What is the UP RERA registration for SAMRIDHI LUXURIYA AVENUE?

The 2026-10-14 Gautam Buddha Nagar extract lists SAMRIDHI LUXURIYA AVENUE as UPRERAPRJ1746. Promoter on that row: SAMRIDHI INFRA SQUARE PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a SAMRIDHI LUXURIYA AVENUE price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean SAMRIDHI LUXURIYA AVENUE is ready to move?

No. The list end date is 29-03-2025. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish SAMRIDHI LUXURIYA AVENUE reviews?

No. This page does not publish star ratings or copied portal reviews.

When was SAMRIDHI LUXURIYA AVENUE registered?

Registration date on the extract: 27-07-2017. Start date on the registered-projects list: 25-02-2017. Declared completion on the summary: 31-12-2022.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.

Other records

Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.