UPRERAPRJ6811

SOLITAIRIAN CITY - (PARY) PHASE-1

SOLITAIRIAN CITY - (PARY) PHASE-1 is on the UP RERA register as UPRERAPRJ6811. Promoter on the list: PARY DEVELOPERS PRIVATE LIMITED. District: Gautam Buddha Nagar. List project type: Residential. List end date: 28-10-2021. Verify on up-rera.in.

Project name
SOLITAIRIAN CITY - (PARY) PHASE-1
Promoter
PARY DEVELOPERS PRIVATE LIMITED
UP RERA registration number
UPRERAPRJ6811
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
Ongoing
Start date on the registered-projects list
08-09-2014
End date on the registered-projects list
28-10-2021
Registration date
31-07-2017
Original start date on the summary
08-09-2014
Modified start date on the summary
08-09-2014
Declared date of completion on the summary
31-07-2019

Extension rows

Extension fromExtension upto
31-07-201930-07-2020
30-07-202029-01-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
29-01-202128-10-2021

Calculated from those dates

Registration to list end date

50 whole months from the registration date 31-07-2017 to the end date on the registered-projects list 28-10-2021.

Original start to declared completion

58 whole months from the original start date 08-09-2014 to the declared completion date 31-07-2019.

Extension rows

The project summary lists 3 extension rows. The last “Extension Upto” text is 28-10-2021.

List end date against declared completion

26 whole months from the declared completion date 31-07-2019 to the list end date 28-10-2021.

List end date against the fetch date

59 whole months from the list end date 28-10-2021 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this SOLITAIRIAN CITY - (PARY) PHASE-1 record

SOLITAIRIAN CITY - (PARY) PHASE-1 is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ6811. The promoter text is PARY DEVELOPERS PRIVATE LIMITED. The project address cell is blank on this row.

The list project type is Residential. The summary project type is Ongoing. Registration date: 31-07-2017. Start date on the list: 08-09-2014. End date on the list: 28-10-2021. Declared completion on the summary: 31-07-2019.

A SOLITAIRIAN CITY - (PARY) PHASE-1 price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about SOLITAIRIAN CITY - (PARY) PHASE-1

What is the UP RERA registration for SOLITAIRIAN CITY - (PARY) PHASE-1?

The 2026-10-14 Gautam Buddha Nagar extract lists SOLITAIRIAN CITY - (PARY) PHASE-1 as UPRERAPRJ6811. Promoter on that row: PARY DEVELOPERS PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a SOLITAIRIAN CITY - (PARY) PHASE-1 price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean SOLITAIRIAN CITY - (PARY) PHASE-1 is ready to move?

No. The list end date is 28-10-2021. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish SOLITAIRIAN CITY - (PARY) PHASE-1 reviews?

No. This page does not publish star ratings or copied portal reviews.

When was SOLITAIRIAN CITY - (PARY) PHASE-1 registered?

Registration date on the extract: 31-07-2017. Start date on the registered-projects list: 08-09-2014. Declared completion on the summary: 31-07-2019.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.

Other records

Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.

WhatsApp