Registration to list end date
58 whole months from the registration date 31-07-2017 to the end date on the registered-projects list 29-06-2022.
UPRERAPRJ6721
SOLITAIRIAN CITY - (SOLI-)PHASE-2 is on the UP RERA register as UPRERAPRJ6721. Promoter on the list: SOLITAIRE REALINFRA PRIVATE LIMITED. Project address: Plot No. GH-B-1/2, Sector-25, Jaypee Greens, Sports City, SDZ, Yamuna Expressway Industrial Authority Area, Gautam Buddha Nagar, Uttar Pradesh, PIN-201310. List project type: Residential. List end date: 29-06-2022. Verify on up-rera.in.
| Extension from | Extension upto |
|---|---|
| 31-12-2020 | 30-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30-06-2021 | 29-06-2022 |
| 29-06-2022 | 28-03-2023 |
58 whole months from the registration date 31-07-2017 to the end date on the registered-projects list 29-06-2022.
75 whole months from the original start date 08-09-2014 to the declared completion date 31-12-2020.
The project summary lists 3 extension rows. The last “Extension Upto” text is 28-03-2023.
17 whole months from the declared completion date 31-12-2020 to the list end date 29-06-2022.
51 whole months from the list end date 29-06-2022 to the fetch date 2026-10-14.
Official UP RERA project summary
List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.
SOLITAIRIAN CITY - (SOLI-)PHASE-2 is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ6721. The promoter text is SOLITAIRE REALINFRA PRIVATE LIMITED. The project address is Plot No. GH-B-1/2, Sector-25, Jaypee Greens, Sports City, SDZ, Yamuna Expressway Industrial Authority Area, Gautam Buddha Nagar, Uttar Pradesh, PIN-201310.
The list project type is Residential. The summary project type is Ongoing. Registration date: 31-07-2017. Start date on the list: 08-09-2014. End date on the list: 29-06-2022. Declared completion on the summary: 31-12-2020.
A SOLITAIRIAN CITY - (SOLI-)PHASE-2 price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.
Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.
The 2026-10-14 Gautam Buddha Nagar extract lists SOLITAIRIAN CITY - (SOLI-)PHASE-2 as UPRERAPRJ6721. Promoter on that row: SOLITAIRE REALINFRA PRIVATE LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.
No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.
No. The list end date is 29-06-2022. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.
No. This page does not publish star ratings or copied portal reviews.
Registration date on the extract: 31-07-2017. Start date on the registered-projects list: 08-09-2014. Declared completion on the summary: 31-12-2020.
Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.
Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.