UPRERAPRJ8319

Supertech Eco Village-3 Phase-3

Supertech Eco Village-3 Phase-3 is on the UP RERA register as UPRERAPRJ8319. Promoter on the list: SUPERTECH LIMITED. District: Gautam Buddha Nagar. List project type: Residential. List end date: 30-11-2021. Verify on up-rera.in.

Project name
Supertech Eco Village-3 Phase-3
Promoter
SUPERTECH LIMITED
UP RERA registration number
UPRERAPRJ8319
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Project address
Not listed on UP RERA
Sector, read from the project address
Not listed on UP RERA
Corridor, read from the project address
Not named in the project address
Project type on the registered-projects list
Residential
Project type on the project summary
Ongoing
Start date on the registered-projects list
31-12-2012
End date on the registered-projects list
30-11-2021
Registration date
08-08-2017
Original start date on the summary
15-10-2010
Modified start date on the summary
31-12-2012
Declared date of completion on the summary
31-05-2021

Extension rows

Extension fromExtension upto
31-05-202130-11-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)

Calculated from those dates

Registration to list end date

51 whole months from the registration date 08-08-2017 to the end date on the registered-projects list 30-11-2021.

Original start to declared completion

127 whole months from the original start date 15-10-2010 to the declared completion date 31-05-2021.

Extension rows

The project summary lists 1 extension row. The last “Extension Upto” text is 30-11-2021 (Six months extension in view of force majeure caused by covid-19 pandemic).

List end date against declared completion

5 whole months from the declared completion date 31-05-2021 to the list end date 30-11-2021.

List end date against the fetch date

58 whole months from the list end date 30-11-2021 to the fetch date 2026-10-14.

Official UP RERA project summary

List source: https://www.up-rera.in/projects. Fetched 2026-10-14. District hub: Gautam Buddha Nagar.

How to read this Supertech Eco Village-3 Phase-3 record

Supertech Eco Village-3 Phase-3 is copied from the UP RERA registered-projects list for Gautam Buddha Nagar, fetched 2026-10-14. The registration number on that row is UPRERAPRJ8319. The promoter text is SUPERTECH LIMITED. The project address cell is blank on this row.

The list project type is Residential. The summary project type is Ongoing. Registration date: 08-08-2017. Start date on the list: 31-12-2012. End date on the list: 30-11-2021. Declared completion on the summary: 31-05-2021.

A Supertech Eco Village-3 Phase-3 price, brochure PDF, floor plan, and payment plan are not part of this extract, so this page does not print them. A list end date is not an occupancy certificate. This page does not publish star ratings or copied portal reviews.

Open the same registration on up-rera.in before you treat a brochure line as the record. Futuristic Noida can walk through the page on a call. That is not a legal opinion and not a promise that the project will be delivered.

Questions about Supertech Eco Village-3 Phase-3

What is the UP RERA registration for Supertech Eco Village-3 Phase-3?

The 2026-10-14 Gautam Buddha Nagar extract lists Supertech Eco Village-3 Phase-3 as UPRERAPRJ8319. Promoter on that row: SUPERTECH LIMITED. Confirm the same number on up-rera.in. This page does not invent a second number.

Is a Supertech Eco Village-3 Phase-3 price, brochure PDF, floor plan, or payment plan on this page?

No. This is the public registration record. It does not host a price list, a brochure PDF, a floor plan, or a payment plan. A missing file is left blank.

Does the list end date mean Supertech Eco Village-3 Phase-3 is ready to move?

No. The list end date is 30-11-2021. The project type on the extract is Ongoing. A list end date is not an occupancy certificate, and this page does not turn it into a ready-to-move claim.

Does this page publish Supertech Eco Village-3 Phase-3 reviews?

No. This page does not publish star ratings or copied portal reviews.

When was Supertech Eco Village-3 Phase-3 registered?

Registration date on the extract: 08-08-2017. Start date on the registered-projects list: 31-12-2012. Declared completion on the summary: 31-05-2021.

Get latest price / site visit

Ask Futuristic Noida for the latest price the developer has shared, or for a site visit. This page does not list a price.

Other records

Data from UP RERA public records as of 14 Oct 2026; verify on up-rera.in. Futuristic Noida is a RERA-registered real estate agent. Names and dates are copied from the portal text, including where that text is shortened.