Short answer: every registered project files a quarterly progress report (QPR) on UP RERA. It shows how far construction has gone, how much money has been collected and how much has been spent. Read the latest QPR and compare it with the declared completion date before you pay any booking amount.
Where to find it
- Go to up-rera.in and search the project by name or RERA number (for example UPRERAPRJ313638/03/2026).
- Open the project details. Look for the progress / QPR section and the uploaded documents.
- Download the latest quarter. If the latest QPR is many quarters old, treat that as a red flag.
What to read in it
| Section | What to check | Red flag |
|---|---|---|
| Tower-wise progress | Floors cast vs total floors; finishing work | Little change across two or three quarters |
| Units booked | How many homes are sold | Very low sales close to the deadline |
| Money collected vs spent | Funds received from buyers and spent on the project | Collected far more than spent |
| Approvals | Building plan, fire, environment NOCs | Pending approvals late in the project |
| Completion date and extensions | Declared date vs any extension | Repeated extensions |
Link it to the escrow rule
Under RERA, 70% of buyer money must go into a separate project account and be used for that project. Read how the 70% escrow account works.
Next checks
- Check RERA status and builder delays
- Verify your broker's RERA number
- RERA date vs actual possession
- RERA approved projects in Noida
If you can't make sense of a QPR, send it to us. We'll read it with you and tell you what it shows, including the bad parts.
Disclosure: Futuristic Noida (Rohit Kumar Jha) is a RERA-registered channel partner for Godrej, Sobha, Stellar and Prestige projects and may earn brokerage from the developer on bookings made through us; this does not change your price. Gains (if any) depend on the market. Images marked "Artistic impression" are not photographs.
General information, not legal, tax or financial advice. Rules change; confirm with a lawyer/CA and the official portal before you pay. Futuristic Noida is a RERA-registered channel partner; brokerage may apply. No returns are promised.
A decade in real estate, including my years at 99acres. Send the document, I'll tell you straight. WhatsApp 9953793147 Request a call-back
FAQ
What is a QPR in RERA?
A quarterly progress report the builder files on the RERA portal showing construction progress, sales and project finances.
How often is a QPR filed?
Every quarter. A missing or very old QPR is a warning sign.
Can a QPR tell me if a project will be delayed?
Not for certain, but slow progress across quarters compared with the time left to the completion date is a strong signal.