Noida & Greater Noida Builder Delay Report 2026

969 UP RERA projects. Every extension, counted.

Get a shortlist and price sheet in your budget
Futuristic Noida is a RERA-registered channel partner. We reply on WhatsApp during business hours.
Key finding: Of 969 projects UP RERA lists in Gautam Buddha Nagar (Noida, Greater Noida, Greater Noida West, Yamuna Expressway), 54% have at least one completion-date extension on record. Where there was an extension, the median shift from the originally declared completion date to the current RERA end date is 6 months. 144 projects have moved 24+ months. 417 projects are past their current RERA end date with no completion or occupancy certificate listed on the portal.
969projects analysed
54%have ≥1 extension
6 momedian shift (extended projects)
417past end date, no CC/OC listed
161labelled "Default on QPR"
165on UP RERA NCLT list

How to cite: Futuristic Noida, "Noida & Greater Noida Builder Delay Report 2026", 24 Oct 2026, futuristicnoida.com/reports/builder-delay-report-2026/, using UP RERA data as of 7 Oct 2026.

1. How many extensions projects took

No extension447
1 extension313
2 extensions119
3+ extensions90

Residential projects only: 57% have ≥1 extension (690 projects). Many 2020–21 extensions were the blanket COVID-19 force-majeure extension; 451 projects have a COVID extension row.

2. How far end dates moved

Shift = months from the originally declared completion date to the latest end date on UP RERA (computed by us from the two portal dates).

0 months449
1–6 months274
7–12 months32
13–24 months70
24+ months144

3. By area (tehsil as listed on UP RERA)

UP RERA rarely states a sector in the address, so we group by the tehsil field. It's a rough proxy: Dadri covers Greater Noida and Greater Noida West, and Gautam Buddha Nagar covers most of Noida.

AreaProjects≥1 extensionMedian shift (mo)CC/OC listedPast end date, no CC/OC
Gautam Buddha Nagar tehsil (mostly Noida)78557%634%362
Dadri tehsil (Greater Noida / GNW)16139%024%45
Tehsil not listed1753%629%10
Jewar tehsil (Yamuna Expressway)60%00%0

4. By year of RERA registration

RegisteredProjects≥1 extensionMedian shift (mo)Past end date, no CC/OC
201760268%6326
20185383%632
20195593%627
20201436%010
20213514%012
20222814%08
2023290%01
20245110%01
2025620%00
2026402%00

Projects registered in 2017 are the legacy stock that was already under construction when RERA began. They carry most of the long delays.

5. By builder group (6+ projects)

The builder groups are our estimate: we matched promoter companies to the brands people know. 529 projects are left ungrouped. This is a count of RERA records, not a rating of any builder. A project with no extension can still be late in practice, and an extension can be lawful.

Group (estimate)Projects≥1 extensionTotal extension rowsMedian shift (mo)CC/OC listedOn NCLT list
Jaiprakash Associates (now Adani Infrastructure Integrated Solutions)4055%2961539
Supertech group3569%286634
AIMS / Gardenia group2662%206100
Gaurs group (Gaursons)2365%166160
Logix group1861%126310
Jaypee Infratech1867%1854100
Uttam Steels consortium (through Ansal Hi-Tech Townships)1889%16600
YEIDA (authority scheme)1638%9000
Antriksh group1681%14620
ATS group1486%15640
Ajnara group1471%186513
Nirala group1331%6080
Panchsheel group1258%15770
Unitech group1258%7600
Nimbus (IITL-Nimbus)1040%6080
GNIDA (authority scheme)1010%2090
Mahagun group989%242720
Ansal group838%4014
Elegant group862%63920
Imperia Structures850%6300
Gulshan group757%4450
Parsvnath Developers771%8606
Eldeco617%1010
Rise / Euphoria667%6600
Three C650%3312

6. Projects from builders we work with

We list these openly because we earn from them. Same method, same columns.

ProjectRERA no.Original completionCurrent end dateExtensionsCC/OC listed
Crown Residences At Godrej Golf LinksUPRERAPRJ438937/04/202606-05-203006-05-20300No
Godrej ArdenUPRERAPRJ110163/08/202515-05-203015-05-20300No
Godrej Avenue 9UPRERAPRJ839208/07/202530-04-203030-04-20300No
Godrej JardiniaUPRERAPRJ288309/04/202403-12-202803-12-20280No
Godrej Majesty Gh-01/B,C,D,E.J And K Sec 12 -G NoidaUPRERAPRJ250823/04/202516-02-203016-02-20300No
Godrej Nest Phase-1UPRERAPRJ1352131-03-202430-09-20241No
Godrej Nest Phase-2UPRERAPRJ1425230-09-202429-03-20251No
Godrej Nurture Phase-1UPRERAPRJ1786129-03-202528-09-20251No
Godrej Palm Retreat 1UPRERAPRJ74560104-12-202403-06-20251Yes
Godrej Palm Retreat 2UPRERAPRJ12463230-12-202530-12-20250No
Godrej RiverineUPRERAPRJ763929/11/202422-09-202922-09-20290No
Godrej Tropical IsleUPRERAPRJ30339007-06-202807-06-20280No
Godrej Woods Phase IiUPRERAPRJ14531828-01-202728-01-20270Yes
Godrej Woods Phase-1UPRERAPRJ70473014-07-202614-07-20260Yes
Godrej Woods Phase-3UPRERAPRJ77353620-10-202720-10-20270No
Park Lane At Godrej Golf LinkUPRERAPRJ1669715-12-202113-06-20232Yes
Sobha AurumUPRERAPRJ361748/06/202530-04-203030-04-20300No
Sobha RivanaUPRERAPRJ313638/03/202607-02-203107-02-20310No
Stellar 1422 Phase IiUPRERAPRJ305571/04/202631-03-202831-03-20280No
Stellar One Phase 1UPRERAPRJ620931-03-202029-09-20201Yes
Stellar One Phase IiUPRERAPRJ92378015-11-202815-11-20280No
Stellar One Phase IiiUPRERAPRJ564504/08/202426-10-202826-10-20280No
The Suites At Godrej Golf LinksUPRERAPRJ237315-07-202213-01-20242Yes
Windsor At Godrej Golf LinksUPRERAPRJ1671215-12-202113-06-20232Yes

What buyers should do with this

  1. Open your project on our RERA check or up-rera.in and read the extension rows yourself.
  2. Ask the builder in writing which tower your unit is in and that tower's own completion date.
  3. Projects past their end date with no CC/OC listed need extra checks: the latest QPR, the escrow account and any NCLT status.
  4. See the builder report card for each promoter's projects, and how to check RERA delay.

Methodology

  • Source: UP RERA public Registered Projects list for Gautam Buddha Nagar, and each project's Project Summary page (original declared completion, extension rows), NCLT list and OC/CC records. All pulled 7–14 Oct 2026, with no login.
  • Scope: 969 projects: 690 residential, 253 commercial and 26 mixed.
  • Shift: latest RERA end date minus original declared completion, in months. It is computed, so treat it as approximate.
  • CC/OC listed: any completion or occupancy certificate row on the portal. Phase-wise certificates count.
  • Not measured: actual handover dates, construction completion %, or quality. UP RERA's QPR progress isn't in this extract.
  • Errors: portal data can be stale or mis-keyed. If you spot one, WhatsApp us with the RERA number and we'll correct it and log the change.
  • Licence: free to cite with a link to this page.

FAQs

What share of Noida projects got a RERA extension?

54% of 969 UP RERA projects in Gautam Buddha Nagar have at least one extension row, as of 7 Oct 2026.

What is the typical delay?

Among extended projects, the median shift from originally declared completion to the current RERA end date is 6 months.

Can I download the data?

Yes, the full CSV is linked at the top of the page and is free to cite with a link.

Is this a builder ranking?

No. It counts RERA records only and does not rate quality or delivery.