Bhutani 18, Sector 128 Noida: the RERA facts, the real progress and what to check before you pay 30%

23 homes in one tower on Jaypee Greens Wish Town land, checked against the UP RERA floor table, the quarterly certificates and the draft agreement.

Quick question on Bhutani 18? Leave your name and mobile. Rohit will call or WhatsApp you.
Request a call-back: +91 99537 93147

Short answer: Bhutani 18 is a single tower of 23 very large homes on plot B-58 in Sector 128, Noida, inside Jaypee Greens Wish Town. It is registered on UP RERA as UPRERAPRJ335396/01/2026, with a declared completion date of 30 Dec 2026. Bhutani publishes no price (“Price on Request”) and asks for 30% at booking and 70% on offer of possession (Bhutani’s official price-list sheet, checked 13 Nov 2026). Three things the sales pitch won’t lead with: the architect certifying the project for UP RERA reported that on 30 Sep 2026 the facade, lifts, fire-fighting and the roads, water and sewage works stood at 0%, with three months left to the RERA date; the “5 BHK of 3,133 sq ft” on the RERA table is only one level of what looks like a duplex; and the land comes through Jaypee Infratech, which signs your agreement as a confirming party.

Floor-by-floor diagram of Bhutani 18 from the UP RERA plan table: two 4 BHK homes on floors 1 and 2, two 5 BHK homes on each odd floor from 3 to 19, zero-home levels on even floors 4 to 20, and a penthouse on floors 21 and 22
Our diagram from the UP RERA plan table for UPRERAPRJ335396/01/2026 (fetched 13 Nov 2026). Not a builder image.

The facts from UP RERA

Bhutani 18 (UP RERA record)
UP RERA numberUPRERAPRJ335396/01/2026, registered 10 Jan 2026 (project type “New”)
PromoterGoodliving Infrastructure Pvt Ltd (promoter ID UPRERAPRM190011), email domain bhutanigroup.com. UP RERA shows 1 registered project for this company, 6 complaints against it (3 still under registration) and 1 complaint on this project
PlotB-58, Sector 128, Jaypee Greens, Noida. One plot of 6,168 sq m (about 1.5 acres)
TimelineProposed start 1 Dec 2025, 13 months; declared completion 30 Dec 2026; no extension on the record
Building permitNoida/Mu.Va.Ni./2021/III-307/1200 dated 10 Jan 2022, valid to 9 Jan 2027, extendable to 9 Jan 2032
Homes23 in one tower (Tower A): 4 × 4 BHK, 18 × 5 BHK and 1 penthouse listed as “Other”. Three basements, ground floor, floors 1–22
Project cost (CA certificate)₹23,498.51 lakh (about ₹235 Cr), of which land ₹3,482.22 lakh and construction ₹19,815.29 lakh
Common facilities on RERAClubhouse of 1,405 sq m with swimming pool and gym; 10 parks totalling 1,724 sq m; 55 KLD sewage plant; one 1,250 kVA transformer
Collection account“M/S. Goodliving Infrastructure Pvt Ltd - RERA Collection Account for Bhutani 18”, ICICI Bank, Sector 137 Noida branch, account ending 2130

From the UP RERA project summary and detail pages and the CA certificate filed at registration (fetched 13 Nov 2026). Check them yourself on up-rera.in or on our RERA record page.

What the RERA floor table actually shows

FloorsWhat the RERA table listsRERA carpetBalcony
1–2Two 4 BHK on each floor (4 homes)3,368 and 3,405 sq ftAbout 1,380 and 1,260 sq ft
3, 5, 7 … 19 (odd floors)Two 5 BHK on each floor (18 homes)3,133 and 3,124 sq ftAbout 1,630 and 1,260 sq ft
4, 6, 8 … 20 (even floors)Two units of area, but 0 homes1,654 and 1,759 sq ftAbout 960 and 610 sq ft
21 + 22One home listed as “Other” on 21, with a 0-home level on 226,487 + 3,877 = 10,364 sq ftAbout 4,150 + 950 sq ft

Source: UP RERA plan table (fetched 13 Nov 2026); square metres converted at 10.764 sq ft and rounded. 4 + 18 + 1 = 23 homes. The table does not use the word “duplex”; that is our reading of the pattern.

  • The 5 BHK is very likely a duplex of about 4,800–4,900 sq ft carpet, not 3,133. Every odd floor from 3 to 19 has two 5 BHKs, and every even floor above it has two blocks of carpet area marked “0 homes”. If each upper level belongs to the home below, a 5 BHK works out to roughly 4,780–4,890 sq ft of carpet, depending on which levels pair up. If anyone quotes you a price “for 3,133 sq ft”, ask which area it is, and get the carpet of both levels in the agreement.
  • “One residence per floor”? Bhutani Group’s project page says the tower is “designed with only one residence per floor”. The RERA table lists two units of area on every floor from 1 to 20. Two duplexes side by side may be what they mean, but ask for the floor plan of your exact unit and check who you share a lift lobby with.
  • The 4 BHKs are on floors 1 and 2. They are single-level homes of about 3,370–3,400 sq ft carpet, the only ones without a second level, and they sit on the lowest floors.
  • The penthouse is about 10,364 sq ft of carpet on floors 21 and 22, plus about 5,100 sq ft of balconies. The provisional fire NOC uploaded to RERA gives the building height as 106.60 m.

Progress: the 30 Dec 2026 date vs what the certificates say

Bar chart of work done on Bhutani 18 by activity on 30 Sep 2026: excavation, basements and stilt 100%, structure slabs 92%, electrical fittings 18%, internal finishes 14%, community buildings (the clubhouse) 41%, and staircases, facade, lifts, fire-fighting and common services 0%
Our chart from the architect’s certificate filed with the Jul–Sep 2026 quarterly report on UP RERA. Not a builder image.

Much of this tower was built before it was registered. The building plan was approved on 10 Jan 2022, and the engineer’s certificate filed for registration (15 Nov 2025) already showed excavation, basements and the stilt floor at 100% and the structure slabs at 86%. The quarterly reports since then, all on UP RERA (fetched 13 Nov 2026):

  • Construction work completed (by cost): 30.95% for Oct–Dec 2025, 30.95% again for Jan–Mar 2026, 38.58% for Apr–Jun 2026 and 39.64% at 30 Sep 2026 (CA certificate dated 31 Oct 2026).
  • By activity on 30 Sep 2026 (architect’s certificate, 26 Oct 2026): slabs 92%, internal walls, plaster and flooring 14%, electrical fittings 18%, community buildings (the clubhouse) 41%. Sanitary fittings, staircases and lift lobbies, facade and waterproofing, lifts, pumps and fire-fighting, roads, water, sewer and the sewage plant: all 0%.
  • The schedule has already slipped against the architect’s own dates. The same certificate gives 1 Jul 2026 as the end date for the facade and for lifts and fire-fighting, and 1 Dec 2026 for the works needed for an occupancy certificate. On 30 Sep all of them stood at 0%. Slabs (end date 1 Apr 2026, at 92%) and internal finishes (end date 1 May 2026, at 14%) are past their own end dates too.

My honest read: I don’t see how this building gets an occupancy certificate by 30 Dec 2026. Expect the promoter to apply for an extension. Section 6 of the RERA Act, 2016 lets UP RERA extend a registration for force majeure, or in reasonable circumstances for up to one year in aggregate. The building permit itself runs to 9 Jan 2027 and is extendable to 9 Jan 2032. None of this means the project is in trouble; it means the date on the RERA page is not the date you should plan your move around. Read how to read a QPR and RERA date vs actual possession.

The money: no buyer has paid in yet

The CA certificate for 30 Sep 2026 shows ₹0 received from allottees since the project started, no loan sanctioned or disbursed, and ₹10,787.72 lakh (about ₹108 Cr, 45.91% of the estimated cost) spent so far, land included. In other words, as of that date the promoter had funded the tower itself, and no money from buyers had come through the RERA accounts.

That cuts both ways. No buyer money has gone into construction so far, and on a 30:70 plan most of yours would be due only when possession is offered. But you would also be among the first buyers in a 23-home building, so there is no resale record or society to talk to, and the price is whatever is negotiated.

The price and the 30:70 plan, and the 10% rule

There is no price on Bhutani Group’s project page or on the price-list sheet (checked 13 Nov 2026), which says “Price On Request”, 30% of basic price at booking and 70% on offer of possession, GST extra. Our Bhutani 18 project page shows no price either, because we only print prices we can source to a dated official page. Ignore any figure you see on listing sites until Bhutani puts one in writing.

The part brokers skip: Section 13 of the RERA Act, 2016 says a promoter cannot take more than 10% of the cost as an advance or application fee before a written agreement for sale is signed and registered. The draft agreement on UP RERA defines the booking amount the same way, as “not be more than 10% of the Total Price”. So pay at most 10% with your application, and the rest of the 30% only after the agreement is registered in your name.

Item (for every ₹1 Cr of basic price)AmountBasis
At booking: 30% of basic price₹30 lakhBhutani’s price-list sheet. Pay no more than 10% (₹10 lakh) until the agreement is registered; see above
GST at 5% on the instalments≈ ₹5 lakhUsual rate for an under-construction home. Ask how GST applies to the 70% if it falls due after the completion certificate; see our GST guide
On offer of possession: 70% of basic price₹70 lakhBhutani’s price-list sheet
Stamp duty at 7%≈ ₹7 lakhOn the higher of price and circle-rate value; see our stamp duty table
Registration at 1%≈ ₹1 lakhAs above
Parking, club, IFMS, power backup, lease rent, utility depositsNot publishedThe draft agreement lists these as extra. Get every one in writing

Illustration only, per ₹1 Cr of basic price, not a quote. GST assumes the usual 5% on an under-construction home; stamp duty and registration rates as in our stamp duty table (official rates on IGRS UP). Your cost sheet will differ.

The land: Jaypee Infratech, Wish Town and a sub-lease

The draft agreement on UP RERA sets out the chain. YEIDA leased 1,232.38 acres in Noida to Jaypee Infratech Ltd (JIL) for 90 years under the Yamuna Expressway concession; 1,072.84 acres of it, in Sectors 128, 129, 131, 133 and 134, is Jaypee Greens Wish Town. An assignment agreement dated 6 Jan 2020 between JIL, Jaiprakash Associates and the developer gave it the development rights to group-housing cluster B-58. That is why:

  • JIL signs your agreement as “Confirming Party”, and you get a sub-lease from a chain that runs through JIL, not a lease straight from the authority (YEIDA). Read sub-lease deed vs conveyance deed.
  • The building plan was issued to JIL. Noida Authority’s approval of 10 Jan 2022 is addressed to Jaypee Infratech and says water and sewage connect through JIL’s drains and mains, with the water connection from JIL.
  • Lease rent is extra. The draft lists lease rent, club charges, power backup, parking and utility connections as outside the total price. Ask for the amounts now, not at possession.

Now the date that matters. JIL was admitted into insolvency on 9 Aug 2017, and the NCLT approved Suraksha’s resolution plan on 7 Mar 2023 (recited in the NCLAT judgment, 21 Feb 2024 (IBBI PDF)). The 6 Jan 2020 assignment was therefore signed while JIL was in insolvency. Jaiprakash Associates, the other party to it, went into its own insolvency on 3 Jun 2024 and has since passed to the Adani group (details in our CRC Peridona review). The advocate’s title report on UP RERA calls the assignment valid and says the plot is free of encumbrances, based on an encumbrance certificate (20 Apr 2023) covering 5 Jan 2020 to 17 Apr 2023. Ask for three things: a copy of the assignment agreement, written confirmation of how it was treated under the Suraksha plan, and a fresh encumbrance certificate, since the one on file stops in April 2023. Background in our Wish Town insolvency guide.

What to fix in the agreement before you sign

UP RERA has three agreement drafts for this project; their files were created on 17 Nov, 17 Dec and 31 Dec 2025. Use the latest (“Agreement to Sub-Lease”). The earliest one carries “For Parmesh Construction Company Ltd.” in its signature footer and names that company as promoter in its notice clause, even though the promoter on RERA is Goodliving Infrastructure. Bhutani’s website footer also shows a different promoter registration number (UPRERAPRM11044). Recital H of the latest draft says any third-party branding is used only under a limited licence and creates no legal obligation on the brand owner, so your contract, and any claims, are with Goodliving Infrastructure, whatever the logo says. Make sure every receipt, allotment letter and agreement names Goodliving Infrastructure and this RERA number. In the latest draft, read these with your lawyer:

  • Clause 7.1 says the promoter will “endeavor” to hand over by a date left blank. Get the date filled in, and make it no later than the RERA date.
  • Clause 7.3 says that for delays beyond the promoter’s control you waive “all rights and claims” to damages. Section 18 of the Act gives you interest for every month of delay; clause 13.2 of the same draft repeats that. Ask how the two fit.
  • Clause 13.2(b): if the promoter defaults and you exit, the draft still deducts cancellation charges (10% of the total price) from your refund. Clause 7.1 and Section 18 of the Act say full refund with interest. Ask for the deduction to be struck out of 13.2(b).
  • Clauses 9.1 and 9.4. Clause 9.1 says that after taking possession you have “no claim” about work or materials, and the defect clause, 9.4, leaves the number of years blank. Section 14(3) of the Act gives you five years from possession to report defects. Get “five years” written into 9.4 and 9.1 made subject to it.
  • Clause 9.8 lets the promoter build more on the plot if a later change in law allows it, with your consent given in advance.
  • Earnest money is 10% of the total price, forfeited if you cancel. On a home of this size that is a large number; know it before you sign.

More in builder-buyer agreement clauses and possession delay compensation under UP RERA.

Who should look at it, and who shouldn’t

Where I land: Bhutani 18 is an unusual product for Noida, a small tower of duplexes and one penthouse just off the expressway, with the structure largely up and no buyer money in it yet. I would judge it on three documents, not on the brochure: the assignment agreement with its treatment under the Suraksha plan, a fresh encumbrance certificate, and a signed agreement with the possession date and the second-level carpet filled in.

  • Consider it if you want a duplex of roughly 4,800 sq ft carpet or a penthouse, in a building with only 23 homes, just off the Noida–Greater Noida Expressway (near Jaypee Hospital on Bhutani’s location map), and you are comfortable with a sub-lease on Wish Town land.
  • Skip it if you need to move in on a fixed date in early 2027, you are not comfortable with a sub-lease that runs YEIDA → Jaypee Infratech → developer rights → you, or you want to see a finished, certified building before you commit. On the same stretch, compare our Sector 128 comparison, L&T Green Reserve review and luxury apartments on the expressway.
  • Before you sit with sales, read our price negotiation guide and is the booking amount refundable. “Price on request” is where negotiation starts, not where it ends.

Check it yourself

  1. Open UPRERAPRJ335396/01/2026 on up-rera.in. Match the promoter (Goodliving Infrastructure), plot B-58, the 30 Dec 2026 date and your unit’s carpet and balcony against the table above, and check under “Quarterly Progress Report” whether a newer quarter or an extension has been posted.
  2. Pay only into the RERA collection account: “M/S. Goodliving Infrastructure Pvt Ltd - RERA Collection Account for Bhutani 18”, ICICI Bank, account ending 2130. It is the same account printed on Bhutani’s price-list sheet. The account ending 2129 that appears in the CA certificate is the RERA separate (70%) account; buyers pay only into the one ending 2130. Never pay a broker or an individual. See how the RERA account works.
  3. Get the unit, both levels’ carpet, balcony, parking, club, lease rent, IFMS and power-backup charges on a signed, dated cost sheet before any cheque. At possession, use our snag list and check the occupancy certificate.
  4. Download our free PDF guides, especially the UP RERA check and the all-in cost worksheet, and run the project through our RERA project checker. Questions? WhatsApp or call us on +91 99537 93147.

Project page: Bhutani 18 project page · RERA record: UPRERAPRJ335396/01/2026 · Also read: site visit questions · carpet vs super area.

Sources: UP RERA project record UPRERAPRJ335396/01/2026 and its uploaded documents and quarterly certificates (fetched 13 Nov 2026); Bhutani Group’s project page and Bhutani’s official price-list sheet (checked 13 Nov 2026); RERA Act, 2016; NCLAT judgment, 21 Feb 2024 (IBBI PDF). Bhutani / Goodliving Infrastructure is not one of the builders we are a channel partner for.

Disclosure: Futuristic Noida (Rohit Kumar Jha) is a RERA-registered channel partner for Godrej, Sobha, Stellar and Prestige projects and may earn brokerage from the developer on bookings made through us; this does not change your price. Gains (if any) depend on the market.

General information, not legal, tax or financial advice. Rules change; confirm with a lawyer/CA and the official portal before you pay. No returns are promised.

Want a second pair of eyes on your papers?
A decade in real estate, including my years at 99acres. Send the document, I'll tell you straight. WhatsApp 9953793147 Request a call-back

FAQ

What is the RERA number of Bhutani 18?

UPRERAPRJ335396/01/2026, registered on 10 Jan 2026. The promoter is Goodliving Infrastructure Pvt Ltd, the plot is B-58, Sector 128, Jaypee Greens, Noida, and the declared completion date is 30 Dec 2026.

What is the price of Bhutani 18?

Bhutani publishes no price; its price-list sheet says “Price On Request”, with 30% of the basic price at booking and 70% on offer of possession, GST extra. Under Section 13 of the RERA Act, pay no more than 10% before the agreement for sale is registered.

What are the flat sizes in Bhutani 18?

On UP RERA: four 4 BHK homes of about 3,370–3,400 sq ft carpet on floors 1–2, eighteen 5 BHK homes listed at about 3,124–3,133 sq ft on odd floors 3–19 with a further 1,654–1,759 sq ft listed on the even floor above (very likely duplexes of about 4,800–4,900 sq ft carpet), and one penthouse of about 10,364 sq ft carpet on floors 21–22. Balconies are listed separately.

Will Bhutani 18 be ready by December 2026?

The RERA date is 30 Dec 2026, but on 30 Sep 2026 the certifying architect put the facade, lifts, fire-fighting and the roads, water and sewage works at 0%, with structure slabs at 92% and internal finishes at 14%. Plan for an extension, and check the latest quarterly report on UP RERA.

Is Bhutani 18 freehold?

No. Like most Noida group housing it is leasehold, but here the lease chain runs through Jaypee Infratech: the land is part of Jaypee Greens Wish Town, leased by YEIDA to Jaypee Infratech for 90 years. The developer holds development rights under a 6 Jan 2020 assignment agreement, Jaypee Infratech signs the agreement as confirming party, and buyers get a sub-lease.