The numbers
| Promoter type | Projects | Ever extended | Shifted 24+ months | CC/OC listed (past end date) | On NCLT list |
|---|---|---|---|---|---|
| Single-project promoter | 270 | 47% | 16% | 44% of 162 | 8% |
| Known builder group | 440 | 56% | 10% | 38% of 356 | 26% |
| Other multi-project promoters | 259 | 57% | 20% | 43% of 185 | 12% |
Source: UP RERA project summaries and NCLT list for Gautam Buddha Nagar, pulled 7 Oct 2026. "Single-project promoter" means a company with one project and not in a known group (our grouping, an estimate). Some are SPVs of larger firms. Full CSV and method: Builder Delay Report 2026.
Checks that matter more than size
- Is the project RERA-registered, with a 70% escrow account? See how the 70% escrow works.
- Look up the promoter's other projects: how to check builder delays.
- Is land cost paid to the Authority? Unpaid dues stall registries.
- Prefer a construction-linked plan, and test your EMI in the EMI calculator.
FAQs
Is it risky to buy from a small builder in Noida?
Somewhat. In UP RERA data, 16% of single-project promoters' projects shifted 24+ months, against 10% for known groups. But known groups are more often on the NCLT list. Check the specific project.
Are big builders safe from insolvency?
No. 26% of projects by known builder groups in Gautam Buddha Nagar are on UP RERA's NCLT list, driven by a few large groups.
What should I check before booking with a new builder?
RERA registration, escrow, the promoter's other projects and delays, land dues to the Authority, and the payment plan.